Call
+44 345 6465 454
callcenter person
Get a quote

atspace engineer with checklist

The project centred around the construction of a Passive House located in a suburban setting. The design incorporated high-quality insulation, airtightness measures, triple-glazed windows, and a mechanical ventilation system with heat recovery. The primary goal was to achieve stringent airtightness levels, ensuring minimal air leakage and maximum energy efficiency.

Air Pressure Testing Process

Air pressure testing, often known as a blower door test, was conducted to assess the building's airtightness. A blower door apparatus, consisting of a powerful fan mounted in an exterior door frame, was used to depressurise or pressurise the house. During the test, the fan creates a pressure differential between the interior and exterior, allowing precise measurement of air leakage. The testing process involved sealing all openings like windows, doors, vents, and other potential leakage points. Once sealed, the fan was activated to either pressurise or depressurise the house gradually. Simultaneously, specialised equipment measured the airflow required to maintain the desired pressure difference, quantifying the air changes per hour at a specific pressure.

Results and Analysis

The air pressure testing revealed an exceptional airtightness performance, surpassing the Passive House standard requirement. The achieved air changes per hour at 50 Pascals (ACH50) were significantly lower than the threshold set by Passive House certification, demonstrating remarkable airtightness. The findings enabled the identification and rectification of minor leaks, contributing to further improvement in airtightness. These adjustments included reinforcing seals around windows and doors, enhancing insulation in certain areas, and addressing any gaps in the building envelope.

Conclusion

Air pressure testing serves as a crucial validation tool in Passive House construction, ensuring the integrity of the building envelope and maximising energy efficiency. The meticulous process not only verifies compliance with stringent standards but also highlights areas for potential improvement. In this case, the meticulous testing and subsequent adjustments led to an even tighter building envelope, reaffirming the project's commitment to sustainability and energy efficiency in the built environment. The successful completion of air pressure testing affirmed the Passive House's exceptional airtightness, setting a benchmark for future projects and emphasising the importance of rigorous quality assurance measures in sustainable construction.

Previous Article: Armthorpe Next Article: Air Permeability Testing in Doncaster by ATSPACE

"ATSPACE has provided , and continues to provide, an outstanding service to a high standard."

Andy Gilliver, Persimmon Homes

Results

 

 

"A very prompt and efficient service that dealt with every aspect of my requirements in a professional way. If you're in need of any testing requirements to meet building regulations I'd recommend ATSPACE every time."

Mynott Associates Limited

Results

"We have Found ATSPACE Services reliable, professional and friendly at a competitive Price."

Lyndsay Thrower, Taylor Wimpey

Results

"Thank you for the Smoke shaft Air Pressure Test. The whole experience with ATSPACE has been a pleasure from the start and we are looking forward to working with you on the next job.”

Brian Keane, C.E.O, Cameron Ventures Group

Results

"Just a note to thank ATSPACE for the excellent service received on this most recent project. Your engineer put himself out to ensure that the Smoke shaft Air Pressure Test was carried out with the minimum of fuss (in a very tricky environment) and was a pleasure to have on site."

Olly Wigg Director, Bowson Leeway Homes

Results

Testimonials

Trusted by 9K+ businesses
hill
taylor wimpey
logo-mace
Willmott_Dixon_logo
Copyright © 2022 Atspace Ltd. Website Design by Insynth Marketing Ltd.